Camp design

Five phases. The OIQ seal is not LPT.

Month 1: studies. Months 2–3: plant. Month 4: pad. 24 h and 48 h are study targets, not a schedule guarantee.

Visual-direction illustration. Does not document an LPT INC. job, vehicle or asset.

Preliminary design and exhaustive technical study of all systems — not intended for construction.

What LPT stamps, what it does not

LPT is RBQ 5734-5225-01. Engineering seals belong to the OIQ named on the file. This page is not a sealed drawing.

The nordic pilot prices after geotech, access and site regime.

Study milestones

PhaseAt LPTTarget proof
1. Design & sealsBIM/CAD, FEA, CFD — project OIQ engineersCSA A277 / NBC drawings
2. Plant prefabPro-Fab/ATCO modules, Toromont, H2O, Starlink skidsBlower-door < 1.0 ACH@50 Pa, 60 psi
3. Logistics & padConvoy, screw piles, dockingStructure assembled < 24 h (study target)
4. MEPDry-Connect, seals, microgridWeathertight building targeted at 48 h
5. HandoverKitchen, Aqua-Loop, Wi-Fi, manualAcceptance — operator takes the camp

Preliminary design and exhaustive technical study of all systems — not intended for construction.

Questions

FAQ

48 hours under contract?+

No. 48 h is a study assembly target once the pad is ready. The mandate takes it, or not.

Industrial | Abatement | Camps

Wherever the camp goes.

Modular camps, industrial assembly, remote pads. Plan. Coordinate. Deliver.